How do I add a variation (change order)?
Open the budget's Change Orders page, click Add New, fill in the details and click Add. A change order adds extra hours and money on top of the budget without changing the original figures.
What a variation is
- Extra work added after the budget is set, for example when the client asks for more.
- In Swift Checkin, variations are called Change Orders.
Steps
- In the left menu, under Finance, click Cost Management, then Budgets, and pick the project.
- In the budget table, click ... on the budget's row and choose Change Orders.
- Click Add New. The Add Change Order panel opens.
- Fill in Name (2 to 50 characters), Description (2 to 200 characters), Quantity (extra hours) and Unit Cost (hourly rate). All are required.
- Click Add. You'll see New budget change order created successfully.
Good to know
- Use a change order whenever the work changes, because a budget's Quantity and Unit Cost can't be edited.
- Once a budget has a change order, the Budget Amount card shows the original amount plus change orders, and the budget table shows a Change Orders column.
- Project member users can view change orders but don't see the Add New button.