Why can't I add or change a budget?

You need an admin role that can manage budgets, the Budgets feature must be on, and the project must already exist.

Common reasons​

What you seeWhyWhat to do
No Add Budget, Edit or DeleteYou have the project member role. Project members can view budgets but not change them.Ask an admin to make the change.
Budgets isn't in the menuThe Budgets feature isn't switched on for your organisation.Ask your account admin or Swift Checkin support.
The project isn't in the listThe project hasn't been created yet.Create the project first.
You can't change Quantity or Unit CostThese can't be edited once the budget is made.Add a change order instead. See How do I add a variation (change order)?
A budget can't be deletedIt came from Autodesk (marked "Indicates from partner account").Budgets from Autodesk can't be deleted in Swift Checkin.

Example​

The client adds 20 extra square metres of tiling to the Harbour Apartments job.

  1. You open the tiling budget to change Quantity, but it can't be edited.
  2. You add a change order for the extra 20 square metres instead.
  3. The Budget Amount card now shows the original amount plus the change order.